Total area to be excavated and prepared for paving

Sets a recommended sub-base depth: patio/path 100mm, driveway 150mm, shed base 125mm

Compacted MOT Type 1 — 10cm patios/paths, 15-20cm driveways. Excavate ~20% deeper to allow for compaction.

Sharp sand blinding layer — typically 3-5cm screeded level

How We Calculate This

This calculator estimates MOT Type 1 sub-base aggregate and sharp sand for paving foundations.

Sub-base

Tonnes = Area × Depth × Density. Compacted MOT Type 1 density is ~1,950 kg/m³ (loose/delivered material is nearer 1,500, so allow for compaction). Lay and compact in ~50mm layers.

Sharp sand

The sand blinding layer sits on top of the sub-base. Typically 30-50mm deep, screeded level as the final bed for slabs. Sharp sand density is ~1,600 kg/m³ air-dry (heavier when damp).

Membrane

On soft or clay ground, lay a permeable geotextile membrane across the whole excavated area beneath the sub-base to stop the aggregate sinking into the subsoil. A weed membrane can also sit just under the paving to suppress weeds through the joints. Allow 10% extra for overlaps (overlap sheets by at least 300mm).

Frequently Asked Questions

Was this calculator helpful?

One tap. Votes are anonymous and carry the page address, your device type, screen size and country, the numbers in the form and the results on screen, so we can check the answer you saw.

Last updated: February 2026

All calculations are estimates based on standard gardening guidelines. Results may vary with soil conditions, climate, and plant varieties.